When does Banyan Tree Beach Residences Oceanus complete?
Banyan Group targets the fourth quarter of 2028, and its own project page describes construction as substantially progressed as of September 2026, with foundations, structure, roofing and plastering largely complete.

At a glance
- Under development
- Mixed by format
- Absolute beachfront
- 16 homes
That is a developer target rather than a contractual handover date, and the two are not the same thing. What binds is the completion date written into the sale and purchase agreement, together with whatever that agreement says happens if the building is late.
Read the rest of the answer
The construction description is useful because it is specific. Foundations, structure, roofing and plastering largely done in September 2026 leaves fit‑out, services and landscaping across the remaining two years, which is a conventional shape for a sixteen‑home building rather than an unusually tight one.
Oceanus is off‑plan, so the purchase is a series of instalments tied to construction progress. Establish in writing whether deposits sit in escrow or are protected against progress, and what happens to your instalments if the schedule moves. Embark Estate is an appointed sales agency for Banyan Group, so we put those questions to the developer directly.
How we know this
Banyan Group's own project page for Oceanus, read on 1 September 2026, and its Property Development Overview, Thailand edition, of 5 February 2026. Appointment signed August 2026. A developer target can move.